Rearranging the “table” to set these rivets.
Continue reading “Bottom main carry through rivets”
Category: 90 – Service Bulletin
Check SB0023
3 DB were released, two for the Rotax engine and one for the nose gear, since I don’t have the engine yet I could only verify SB0023.
Continue reading “Check SB0023”
Eyebolts and pushrods
I received the new eyebolts from TAF because non of my original eyebolts were okay according to SB0020. With the new eyebolts I could install the pushrods.
Continue reading “Eyebolts and pushrods”
Verify eyebolts according SB0020
Recently SB0020 was released which requires verifying all eyebolts.
Continue reading “Verify eyebolts according SB0020”
Fuselage bottom skin preparation
Several tasks were done to the fuselage bottom skin.
Continue reading “Fuselage bottom skin preparation”
SB0018 heat shrink
The 6:1 heat shrink arrived so I thought to finish SB0018.
Continue reading “SB0018 heat shrink”
SB0018 inspection rudder cables oval sleeves
Since the rudder cables are not yet installed, it’s a good moment to execute SB0018.
Continue reading “SB0018 inspection rudder cables oval sleeves”
Test fit RF rib 6-9
Between the inventory I was looking forward to assembling some parts, so I started with ribs 6 to 9 of the rear fuselage.
Continue reading “Test fit RF rib 6-9”
Rivet both fuel tanks to the wing
This is a milestone in building the wings because when the wings are attached to the wing the jigs can be removed.
Continue reading “Rivet both fuel tanks to the wing”
SB0014
Executing SB0014 and replacing the aluminium rivets with stainless steel rivets.
Continue reading “SB0014”